How Long Does a Subdivision Take in Melbourne?

Jan 2, 2026Subdivision
How Long Does a Subdivision Take in Melbourne?

Subdivision in Melbourne typically takes 6-12 months from start to finish. A straightforward 2-lot subdivision with no complications usually takes 6-8 months.

Complex subdivisions with infrastructure requirements or multiple lots can take 12-18 months or longer.

Council DA Assessment Time

Council DA assessment for subdivision in Melbourne typically takes 3-6 months. Simple subdivisions may be approved in 6-10 weeks, while complex applications can take 6+ months.

Factors affecting timeframe include:

  • Council workload
  • Completeness of application
  • Whether additional information is requested

Fastest Way to Subdivide

The fastest way to subdivide in Melbourne is a complying development certificate (CDC) subdivision, which can be approved in 20 days.

However, CDC subdivisions have strict criteria - the land must meet minimum lot sizes without variations, and no easements or restrictions can be created. Most subdivisions require a DA.

Survey Work Timeline

The survey work for subdivision typically takes 4-8 weeks total. This includes:

  1. Initial boundary identification and plan preparation: 2-4 weeks
  2. Any revisions required by council: 1-2 weeks
  3. Final survey after DA approval: 1-2 weeks

Actual time on your property is usually just 1-2 days.

VIC LRS Registration Time

Registration with VIC Land Registry Services (LRS) typically takes 2-4 weeks after lodgement. The plan is examined, registered, and new titles are created.

Once registered, your subdivision is complete and lots can be sold or developed separately.